Bridge in the length of approx 560.0 m overpassing Cross Israel road with spans up to 42.0 m. The bridge is made of three sections – one main section designed and executed in Incremental Launching Method and two cast in situ end blocks.
Investor: Israeli Railways
Contractor: Linom Ltd.
Design period: 2004 – 2006
Cost of design: 45,000,000.00 NIS
General Data:
Length: Aprox 56.0 m
Width: 11.0 m
The bridge is made of the three separate superstructures that are joined to a final equable structure – Main bridge in the length of approx 200.0 m designed and built in the Incremental Launching Method.
Two outer superstructures are prestressed slabs cast on situ on embankment with up-down erection method.