NATBAG MODEIN RW LINE N.

Bridge in a total length of approx. 1100.0 m made of four structures.

Investor: Israeli Railways

Contractor: Solel-Bone Ltd.

Design period: 2003-2006

Cost of design: Approx. 60,000,000 NIS

General Data:

Length: Approx. 1100.0 m

Width: 11.0 m

The bridge is made of four separate bridges:

Bridge 1.1 – length is about 300.0 m built in Balanced Cantilever Method by special form work.

Main spans of the road between them 72.0 m.

Bridge 1.2 – overpass over entrance and exit roads from Natbag, made of precast beams in trapezoid cross section. Total length – Approx 155.0 m, Maximal span 42.0 m.

Bridge 1.3 in the open section between the entrance road to Natbag and road number 1 made of precast beams in canal cross section.

Total length of the bridge approx 335.0 m. Span 33.0 m.

Bridge 1.4 overpass over road number 1 in box cross section made in Incremental Launching Method. Total length of the bridge approx 280.0 m spans up to 66.0m.